Fulshear starts its five-year update of water and sewer impact fees
A citizen committee has begun reviewing the one-time fees new construction pays for water and sewer. Today a new home on a 3/4-inch meter pays $28,881.65.

Key facts
- Who: The City of Fulshear's Capital Improvements Advisory Committee, with engineering firm Freese & Nichols presenting.
- What: A workshop to start updating the city's water and wastewater impact fees, the one-time charges new development pays toward the pipes and plants built to serve growth.
- When: The committee met Monday, Oct. 5, 2026. The presentation's timeline puts adoption of updated fees on Sept. 20, 2027.
- Where: Fulshear Municipal Complex, 6611 W. Cross Creek Bend Lane.
- What it means for residents: The current fees, adopted in September 2022, total $28,881.65 for a new home with a 3/4-inch meter. The update will set new amounts, and nothing in the packet says yet whether they will go up or down.
Fulshear has started the work of resetting the one-time fees that new homes and businesses pay toward the city's water and sewer system. The city's Capital Improvements Advisory Committee met on Oct. 5 to choose a chair and vice chair, and the main item was an "Impact Fees 101" presentation from the engineering firm Freese & Nichols on updating the water and wastewater fees.
Texas law requires cities that charge these fees to update them every five years. Fulshear's current fees were adopted in September 2022.
What the fees pay for
The presentation describes an impact fee as a one-time charge on new development for part of the cost of specific capital projects. The question it poses is simple: who pays for the infrastructure that serves growth? With impact fees, new development shares the cost. Without them, existing and future ratepayers cover all of it.
The fees can go toward:
- Construction of projects in the city's 10-year capital improvements plan
- Recently built projects that have extra capacity for growth over the next 10 years
- Survey, engineering and land costs for those projects
- Debt payments on those projects, and the cost of the fee study itself
They can't pay for repairs, operations or maintenance, upgrades that only serve existing customers, or the city's cost of running the program.
What new construction pays today
The current fees are based on water meter size. The packet lists these totals for water plus wastewater:
- 3/4-inch meter, which the study counts as one single-family connection: $28,881.65 ($7,202.97 water and $21,678.68 wastewater)
- 1-inch meter: $49,098.81
- 2-inch meter: $144,408.25
The presentation lists impact-fee capital costs of about $50.7 million for water and $78.1 million for wastewater. The fee formula takes the eligible 10-year project cost, subtracts a credit for the share of utility bills that already goes toward those projects, and divides by the expected growth in home-equivalent connections between 2026 and 2036.
What happens next
The timeline in the packet runs about 12 months. The steps are new 10-year land use assumptions, a water model update, a draft capital plan, a financial audit expected to be finished and on display by the end of April 2027, and then the fee calculations. The timeline marks Sept. 20, 2027, for adoption.
The committee's job is to guide the study, comment on the growth assumptions and project list, and send written comments on the recommended fees to City Council at least five business days before a public hearing. Council sets the final fees. After adoption, the committee files reports twice a year on how the plan is going.
The committee members listed on the agenda are Tajana Surlan, Patrick Dodd, Scott Israelson, William Dampier and Satya Yalamanchili. Minutes from the Oct. 5 meeting haven't been posted yet. The agenda and the full presentation are in the city's Oct. 5 committee packet.
Questions and answers
What is an impact fee in Fulshear?
It's a one-time charge on new development that pays for part of the water and wastewater projects needed to serve growth. Texas law, Chapter 395 of the Local Government Code, governs how cities set them and requires an update every five years.
How much are Fulshear's water and sewer impact fees now?
Under the fees adopted in September 2022, a 3/4-inch meter pays $7,202.97 for water and $21,678.68 for wastewater, or $28,881.65 total. A 1-inch meter pays $49,098.81 total.
Do existing homeowners pay impact fees?
No. Impact fees are charged to new development. The presentation explains that without them, existing and future ratepayers would cover the full cost of growth-related projects through utility bills.
When can residents weigh in?
The update ends with a public hearing before City Council. The committee must send its written recommendation to council at least five business days before that hearing.
Sources
- City of Fulshear — Capital Improvements Advisory Committee agenda and packet, Oct. 5, 2026
- City of Fulshear — Agendas and meeting video (Granicus)
Last verified .
More stories
City Hall
Fulshear restated its outdoor lighting rules in April
Fulshear says more outdoor lights miss city rules. Fixtures must aim down, limit glare, and stay below the roof line.
Community
Fulshear's youth commission may build a volunteer hub for students
On Oct. 15, the Youth Advisory Commission is set to pick its year-long project: connecting students who need service hours with local groups that need help.
Community
Youth soccer group pitches a new layout for Eagle Landing's Field D
Fulshear Youth Soccer wants nine small fields at Eagle Landing's Field D and partner status. Staff back the new layout, not the partnership as written.