A splash pad with a silver windmill-shaped water feature topped by a red wheel, with a playground of green and blue slides and shaded towers behind it.
Photo: Larry D. Moore, via Wikimedia Commons (CC BY 4.0), cropped and resized. A splash pad in Georgetown, Texas, not at Super Dave's All Abilities Park.Photo: Larry D. Moore (cropped and resized) / CC BY 4.0 / Source

Key facts

  • What passed: Change Order No. 3 with contractor DL Meacham, L.P. (Item 28.B), approved unanimously by Fort Bend County Commissioners Court on Monday, Nov. 23, 2026.
  • Cost: $12,966, raising the construction contract to a maximum of $2,449,411.31, paid from county parks bonds.
  • What it adds: Three flood lights on existing poles in the parking area, two new light poles, a double entry gate and two signs, including a second splash pad rules sign.
  • Schedule: The contract now runs through March 7, 2027. That's the end of the construction contract, not an announced opening date.
  • Where: 4200 Fulshear Katy Road. The park has a Katy mailing address, and its parking work uses City of Fulshear right-of-way on Fulshear Katy Road under a 2025 agreement.

Super Dave's All Abilities Park on Fulshear Katy Road will get lights in its parking area, a double gate at the entrance and a couple of new signs before construction wraps up. Fort Bend County Commissioners Court approved the $12,966 change order on Monday, Nov. 23.

The item passed without discussion. In the county's meeting video, commissioners approved purchasing items 28.B through 28.K on one motion, and the vote was unanimous.

What the money buys

The change order combines three requests from the contractor, DL Meacham, L.P.:

  • Parking area lighting ($11,776): Three LED flood lights mounted on power poles already in the parking area, plus two new light poles.
  • A double entry gate (no added cost): A second gate at the park entrance, covered by credits for chain-link and iron fencing the project no longer needs.
  • Signs ($1,190): A maintenance sign and a second set of splash pad rules.

The work adds 60 days to the job, so the construction contract now runs through March 7, 2027. The contract can now total no more than $2,449,411.31, up from $2,328,968.79 when the county awarded it in August 2025. The money comes from county parks bonds.

Don't circle March on the calendar yet

March 7 is the end date of the contractor's contract period. The county hasn't announced an opening date for the park.

The Fulshear connection

The county lists the park at 4200 Fulshear Katy Road, with a Katy mailing address. In March 2025, Fulshear City Council approved an agreement allowing the county to use part of the city's right-of-way on Fulshear Katy Road for the park's parking improvements. The city still owns the road.

Also on Monday's agenda

As part of the consent agenda, which passed unanimously, the court set a Jan. 14, 2027 public hearing on traffic control plans for the Fulshear Lakes Way Street Dedication Section 1.

Questions and answers

So the park opens in March?

Not necessarily. March 7, 2027 is when the contractor's contract period ends. The county hasn't announced an opening date on its park page.

Was there any debate?

No. In the county's meeting video, the court approved purchasing items 28.B through 28.K together on a single motion, and it passed unanimously. Item 28.A was pulled from the agenda.

How much has the contract grown?

The construction contract started at $2,328,968.79 in August 2025. With this third change order, it can now total no more than $2,449,411.31.

Is the park inside Fulshear city limits?

The county lists the park at 4200 Fulshear Katy Road with a Katy mailing address and doesn't say it's inside the city. Fulshear's link is the road: in March 2025, City Council agreed to let the county use part of the city's Fulshear Katy Road right-of-way for parking improvements for the park.

Sources

Last verified .